April 2017: Modular Buildings Delivered!

What an exciting week! We are thrilled to announce that the modular buildings for the Freeman Commons and the Knoll classrooms are being installed.
Here are some specifics:
  • Foundations for the Freeman Commons and all three Knoll Buildings have been completed.
  • A more than 1 million pound crane arrived and was assembled on campus today.
  • The modular building manufacturer has started placing buildings with the crane onto the Freeman Commons foundation first, then will be working back to front on the Knoll Buildings. This should take 4 to 5 business days.
  • Once the modular buildings are in place, work will be done for about 75-90 days to complete the interior and exterior finishes of the buildings.
  • We will communicate more specific dates as we get closer, but we expect the Freeman Commons to be ready to use in mid-to-late July and the knoll buildings by mid-August.